City of Walla Walla
Home GO Menu2024 West Moore Street Sidewalk CDBG
Updated: Aug. 9, 2024
Project Update
The City of Walla Walla Public Works Department will be installing new sidewalk/ADA ramps on the south side of West Moore Street between 4th Avenue and 9th Avenue. The project will also include underground storm system improvements.
Project Schedule
The project is scheduled to begin construction on Monday, August 12, 2024.
How will this project be funded?
This project utilizes 2023 and 2024 Community Development Block Grant (CDBG) funds provided through the Department of Housing and Urban Development, as well as funds from a Transportation Improvement Board (TIB) Complete Streets Grant.
Project Area: